A client undertook the replacement of two hotwell tanks that were nearing the end of their life in their existing plant.
They requested a mechanical engineer seconded from Arka to fulfill the role of Project Engineer. Contributions included:
Our work included numerous design changes to mitigate the factors that led to the deterioration of the previous tanks:
The two tanks were installed in a working plant with two separate outages that only allowed one tank at a time to be taken offline within a strict window.